Thursday, December 23, 2010

Agreed!

We agreed on our final design and I put money down. Now we're committed.

Jill thinks that the cabinets, always the critical path, will be done in about four weeks, making our tentative start date around 1/24/2011.

We still need to pick out the granite for the radiator cover in the foyer. We'll do then whenever Jill has something cool for us to look at.

Here are the preliminary drawings. (The sink and fixture are wrong)

Thursday, December 9, 2010

Close To A Design

Jill--

Starting with your original design dated 10/13/2010, let's make the following changes:

  • Two piece Kohler toilet
  • No crown molding in either area
  • 19" vanity w/ glass vessel
  • No picture light in the entrance way
We want to stick with the cabinets you originally proposed with the glass & LED lighting on the south wall and the bottom drawer on the vanity cabinet. We also want the glass, pendant lights (similar to the dining room).

A couple other repair items I'd like your to include would be the closet doors in the entrance was (the rollers are not working properly), a new latch on the 2nd floor medicine cabinet, and, as we discussed, the dishwasher mounting brackets.

I think that's everything that we talked about, but I'm probably forgetting something.

Let me know if you need anything else. Otherwise, I'll see you Tuesday.

--Matt
Enhanced by Zemanta