Thursday, January 13, 2011

Starting January 18, 2011

Here's the tentative schedule:

Matt:

Schedule for bathroom has been established (so far) as follows, all arrivals approximately 8:30. Please have spaced removed of all personal belongings prior to start. Will you be there the morning of the 18th, or will you leave a key? We will install a lock box.

Tuesday, Jan 18th, HVAC to demo radiators, measure for countertop for vanity and vestibule top

Wednesday, Jan 19th demo and build new wall behind toilet (confirmed)

Thursday, Jan 20th, rough electric (confirmed)

Friday, Jan 21st, electrical inspection

Monday, Jan 24th, spray insulation (confirmed)

Tuesday, Jan 25th, insulation inspection

Wednesday, Thursday, Friday Jan 26th-30th, drywall (waiting on confirmation)

Monday, Jan 31st, tile floor (subject to above)

Tuesday, Feb 1st, grout floor (mirror tile cannot be installed until cabs go in and new window framing is installed) (subject to above)

All for now….

Jill

P.S. We will need to finalize granite for vestibule countertop. I have my eye on a couple of pieces of stone. You and Laurie will need to stop by during daylight hours to take a look at materials, the light in the storage barn is not sufficient after it gets dark out.

P.P.S. Ray wants to know if you may want to consider retiling the front vestibule “while the radiator is removed”, it would be the best time to consider redoing that area.Enhanced by Zemanta